Major Sporting Infrastructure Upgrade (Qatar) Establishing

Establishing entitlement within a fast-track and acceleration-driven delivery environment

Contract management, contract administration, and development of Extension of Time, prolongation cost, and acceleration claims across a high-profile infrastructure upgrade impacted by continuous design changes and complex delivery constraints.

Context

A fast-track infrastructure upgrade programme involving rehabilitation works to a premium sporting facility, associated assets, and major utility networks delivered under a re-measurable contract. The scope comprised civil, structural, and infrastructure works, including surface upgrades, drainage systems, safety installations, underground structures, and external works, executed within a live operational environment.

The project was executed within a compressed timeframe and a fast-track delivery environment, requiring continuous alignment between design development, instructed variations, and works execution.

Commercial & Contractual Challenge

The project was impacted by delay arising from continuous design development and late issuance of design information, resulting in abortive works and re-sequencing across multiple work areas as well as significant additiona scope of work.

These impacts were compounded by delays in technical responses and approvals, which constrained procurement and construction activities and affected planned execution. In parallel, constraints in inspection, approval, and handing-over processes led to deferred acceptance of completed works, impacting testing, commissioning, and progression towards completion.

Collectively, these conditions disrupted planned sequencing and necessitated acceleration measures to maintain programme objectives within a compressed delivery timeframe.

Our Approach

Provided integrated contract management and contract administration services from an early stage of the project, establishing a structured contractual framework that ensured compliance with notice provisions, contemporaneous record-keeping, and systematic administration of contractual processes. This early intervention safeguarded the Contractor’s entitlement and created a structured foundation for subsequent claims.

Established entitlement to additional time through the preparation and substantiation of Extension of Time submissions aligned with contractual requirements and supported by programme-based analysis and contemporaneous records. Prolongation costs arising from extended duration were contractually justified and substantiated through detailed analysis of time-related cost records, quantifying the recoverable cost associated with the extended duration of the Works.

In parallel, structured and advanced acceleration claims to address additional resources deployed to maintain programme objectives, linking acceleration measures to the underlying causes of delay and demonstrating entitlement to associated cost in accordance with the Contract.

All entitlement positions were aligned with the Contract, demonstrating compliance with contractual provisions, substantiation requirements, and causation principles across Extension of Time, prolongation, and acceleration claims.

Impact

Defined a substantiated and defensible basis for recovery, reducing exposure to unrecovered costs and advancing the Contractor’s commercial position across entitlement to time, prolongation cost, and acceleration, supporting favourable claim resolution.